Dear Willie,

I plan to run twice-daily UM model runs between 8 Jan 2011 and 8 Feb 2011 (initialised at 00 and 12 UTC) on MONSooN. Are you able to get me MetOffice? operational analysis data for each of the required start dates?

Many thanks,

Andrew

Change History (9)

comment:1 Changed 3 years ago by anmcr

Hi,

Grenville mentioned last week that Willie was on holiday, is this the reason for the delay in getting the files?

Best wishes,

Andrew

comment:2 Changed 3 years ago by ros

Hi Andrew,

Sorry for the delay in obtaining the startdumps. Willie is back next week and will be able to get them for you then.

Regards,
Ros.

comment:3 Changed 3 years ago by willie

Hi Andrew,

Do you want two start dumps or two per day for 31 days?

Willie

comment:4 Changed 3 years ago by anmcr

Hi Willie,

Its two per day for 31 days.

Thanks,

Andrew

comment:5 Changed 3 years ago by willie

Hi Andrew,

Your data is now ready on MONSooN in /projects/umadmin/wmcgin/data_xfer. Please copy it to your own work space as soon as possible.

64 files, 585 GB.

Willie

comment:6 Changed 3 years ago by anmcr

Dear Willie,

I'm copying over the data now.

The files for 8 Jan 2011 seem to be missing (ie 20110108_qwqg00.T+0 and 20110108_qwqg12.T+0).

Could you please retrieve these as well.

Many thanks,

Andrew

comment:7 Changed 3 years ago by willie

Hi Andrew,

They're there now.

Willie

comment:8 Changed 3 years ago by anmcr

Dear Willie,

I have copied all the data over.

Many thanks,

Andrew

comment:9 Changed 3 years ago by willie

  • Resolution set to completed
  • Status changed from new to closed